The road reconstruction project on McLeod County Road 3 (120th Street) between County Road 1 and County Road 3 is now open to all traffic.

The reconstruction project on County Road 3 (122nd Street) between County Road 9 and Carver County will officially open to all traffic late next week. Officials say there are still some traffic signs that are scheduled to be installed early next week, weather permitting.

The reconstruction project on County Road 15 (Falcon Avenue) between County Road 22 and State Hwy 7 will remain closed due to a remaining centerline culvert that needs to be installed. That work is tentatively scheduled for next week (August 12).